Suzuki Liana since 2002
1. Operation and maintenance of the car
2. Engine
2.1. Preliminary checks
2.1.1. Check of a driving belt
2.1.2. Replacement of an oil filter
2.1.3. Check of a compression
2.1.4. Engine vacuum check
2.1.5. Check of gaps in the drive of valves
2.1.6. Check of level of cooling liquid
2.1.7. Check and cleaning of the cooling system of the engine
2.1.8. Check of the mode of a cut-off of supply of fuel
2.1.9. Check of a spark of ignition
2.1.10. Removal and installation of a high-voltage wire
2.1.11. Check of a high-voltage wire
2.1.12. Removal and installation of a spark plug
2.1.13. Check of a spark plug
2.1.14. Removal and installation of the coil of ignition (with igniter)
2.1.15. Check of the coil of ignition (with igniter)
2.1.16. Check of installation of a corner of an advancing of ignition
2.2. Mechanical part of engines
2.3. Engine cooling system
2.4. Engine lubrication system
2.5. Fuel system
2.6. System of ignition
2.7. System of release
2.8. The engine and system of decrease in toxicity of the fulfilled gases (M13 and M16 engines)
2.9. Tables
3. Transmission
4. Running gear
5. Steering mechanism
6. Brake system
7. Onboard electric equipment
8. Body
9. Schemes of electric equipment
 










2-1-15-proverka-katushki-zazhiganiya-s-vosplamenitelem.html

2.1.15. Check of the coil of ignition (with igniter)

Fig. 2.32. Measurement of resistance of a secondary winding


Measure resistance of a secondary winding (fig. 2.32).
If resistance – differs from norm, replace the ignition coil.
Resistance of a secondary winding is 7,6–10,2 kOhm at 20 °C.

"previous page
2.1.14. Removal and installation of the coil of ignition (with igniter)
following page"